Prayagraj DM Inspects 6-Lane Bridge, Threatens FIR Against Executing Agency If One Side Is Not Completed by December 10

Prayagraj DM Manish Kumar Verma inspected the under-construction 6-lane bridge and convention center, warning the executing agency of an FIR if work misses the December 10 deadline. #PrayagrajNews #DMManishKumarVerma #Prayagraj #6LaneBridge #UPNews #Infrastructure #BreakingNews #PDA #UttarPradeshNews #Development

Nov 26, 2026 - 21:45
0 4
Prayagraj DM Inspects 6-Lane Bridge, Threatens FIR Against Executing Agency If One Side Is Not Completed by December 10

Prayagraj. Taking a stern stance against infrastructure delays, Prayagraj District Magistrate Manish Kumar Verma conducted an on-site inspection of the under-construction 6-lane bridge on Thursday alongside Prayagraj Development Authority (PDA) Vice Chairman Rishiraj and Municipal Commissioner Seelam Sai Teja. Expressing strong displeasure over the sluggish pace of construction, the DM issued strict directives to the executing agency to mandatorily complete one side of the bridge by December 10.

issuing a stern ultimatum, DM Verma warned that if the stipulated deadline of December 10 is missed, an FIR will be registered against the executing agency along with other stringent punitive actions. He instructed the contractors to ramp up machinery and manpower immediately to accelerate progress while ensuring zero compromise on construction quality and adhering strictly to all bridge safety standards.

To ensure daily accountability, the District Magistrate appointed a Setu Nigam (Bridge Corporation) official as the nodal officer, directing them to submit daily progress reports on the bridge's construction. Senior officials from all concerned departments and representatives of the executing agency were present during the inspection.

In continuation of his review, DM Verma also visited the under-construction Convention Center (Cultural Complex) located adjacent to the Science Faculty campus. Inspecting the ongoing civil works, he directed the executing agency to ensure high-quality finishing and complete the entire project by December 10 without fail.

(Zainul Abdin)